PROJECT CASE STUDY

Rainman Watermaker Installation

Rainman watermaker installation designed to give the owners a dependable supply of fresh water and greater freedom to spend time away from marina facilities.

YACHT

Valiant 40

PROJECT TYPE

Watermaker

LOCATION

Grenada

DURATION

1 Week

COMPLETED

January 2026

01

The Owner's Goal

The owners were preparing for longer periods of Caribbean cruising and wanted to reduce their dependence on marinas and shoreside water supplies.

Their existing freshwater capacity was sufficient for short passages, but regular refilling limited how long they could comfortably remain at anchor. They wanted a reliable system that would be straightforward to operate, economical to maintain and suitable for the available installation space aboard. Their main objectives were to achieve:

02

The Challenges

Existing Plumbing

The watermaker needed to integrate with the yacht’s existing freshwater tanks and pipework while maintaining a clear and practical system layout.

Limited Space

The yacht had limited machinery-space access, so the system components needed to be positioned carefully without restricting future inspection and servicing.

Ease of Operation

The owners wanted a system that could be operated confidently without complicated procedures or excessive daily maintenance.

03

Our Solution

After reviewing the owners’ expected water use, cruising plans and available installation areas, we recommended a Rainman watermaker suited to the yacht’s requirements.

The installation was planned around accessibility, ventilation and future maintenance. We coordinated the intake, filtration, high-pressure components, product-water connection and system controls to create a clean and dependable installation.

The complete system was tested and commissioned before handover, and the owners were shown how to operate, flush and maintain it correctly.

04

Scope of Work

  • Review freshwater production requirements
  • Inspect available installation spaces
  • Select the appropriate Rainman system
  • Plan seawater intake and discharge
  • Install pre-filters and system components
  • Connect product water to the yacht’s tanks
  • Install controls and monitoring
  • Flush and pressure-test the system
  • Test freshwater production and quality
  • Provide owner handover and maintenance guidance
05

Equipment Installed

WATERMAKER
Pre-filtration system
Seawater intake components
Product-water monitoring
Freshwater tank connection
System controls & protection
06

The Results

The yacht now has a reliable onboard source of fresh water, allowing the owners to spend longer periods at anchor without planning regular marina visits for water.

More Time at Anchor

Significantly increased energy and water independence.

Greater Independence

The owners can produce fresh water wherever suitable seawater conditions allow.

Straightforward Operation

The system is accessible, clearly arranged and simple to operate and maintain.